News
CAPACITY TEST:

Georgia Power Filings Show 3.2GW Grid Queue Before OpenAI Camellia Debut

Newsroom brief

Data Center Knowledge reviewed PSC filings that recorded a 3,200MW customer commitment and an anonymised 3,210MW project before OpenAI unveiled its $20 billion Project Camellia AI campus.

Verified against source materialEdited by SendTech Times Cloud & Infrastructure DeskSource: Data Center Knowledge
Georgia Power Filings Show 3.2GW Grid Queue Before OpenAI Camellia Debut
Image source: Data Center Knowledge

A 3.2GW AI campus was moving through Georgia utility planning before OpenAI gave the project a public name.

Data Center Knowledge reviewed Georgia Public Service Commission filings that recorded a 3,200MW customer commitment and an anonymized 3,210MW project before OpenAI unveiled the $20 billion Project Camellia campus.

The PSC record establishes the load sequence before the public launch, but it does not identify the confidential customer.

Project Camellia was announced as a 3.2GW AI campus, and the filing material shows how large-load planning can begin months before communities, developers, and other power users see the named project.

PSC Filings Recorded A 3,200MW Commitment

In a first-quarter 2026 large-load filing, Georgia Power recorded 3,200MW of new customer commitments for April 2026 and placed the fuller update in the next quarterly cycle.

OpenAI gave Project Camellia its public name three months after that April commitment appeared in the utility record.

An accompanying planning attachment identifies an anonymized project in technical review with an announced load of 3,210MW, an initial in-service date of Q2 2028, and a ramp to approximately 3.2GW by 2031.

The timeline broadly matches OpenAI's plan to energize the campus in phases beginning in 2028.

Neil Osnato, founder of Persistence Analytics Group, noted that the proposed 3.2GW draw was exceptional for utility planning.

His assessment treated the campus as a system-level load, not a conventional customer connection.

Georgia Power Raised Its Load Forecast

Georgia Power's January 2025 Integrated Resource Plan provides the planning context for early confidential evaluations.

The filing describes ongoing utility talks with large power users and incorporates both prospective and committed projects into long-term demand modeling.

The utility raised its load-growth forecast to 8,200MW through the winter of 2030-31, exceeding the 2023 IRP update by more than 2,200MW, and projected nearly 6,000MW of new demand by the winter of 2028-29.

The filing also proposed new generation resources and strategic transmission investments.

Whether Project Camellia contributed to that forecast cannot be determined from the public record.

A single 3.2GW campus illustrates the size of customer requests that can alter a utility's planning horizon before the project enters local economic-development debate and before local documents name the buyer.

OpenAI Deal Includes Demand Response Terms

Georgia Power's OpenAI agreement carried terms that were not visible in the PSC filings.

The utility put OpenAI under responsibility for full infrastructure and electric-service costs, financial assurances designed to protect existing customers and a 25-year agreement that includes up to 1,000MW of flexible demand response.

Under that arrangement, peak-demand periods can trigger reductions in power delivered to the campus.

The utility described the clause as one of the largest demand-response commitments attached to a single facility in the United States, making curtailment a formal part of the campus's grid connection rather than an afterthought.

Discovery responses in the PSC docket also illustrate how Georgia Power weighs large-load evidence.

Executed electric-service contracts carry more weight in forecasts than service requests, and one proposed data-center project left the queue after the developer stopped responding, lacked an operator, and no longer marketed the site as a data-center location.

Georgia Power's March 31 large-load materials reported committed large-load customers at 12.4GW, the economic-development pipeline at 76.2GW, and committed projects at 31, most of them data centres.

Those figures place Project Camellia within a much larger queue of AI and hyperscale power requests across the utility system.

Public Records Stop Before Customer Confirmation

County-level records add another boundary around the timeline.

The Effingham County Board of Commissioners had no Project Camellia references in agendas, meeting packets, or minutes before the announcement, and its open-records response found no maintained development, incentive, or correspondence files matching the request.

OpenAI has pledged to share Project Camellia water-use data, publish annual independent audits, and maintain community communication.

That transparency commitment begins after the named campus enters public view; the PSC timeline captures the earlier layer where large-load planning can appear under confidential customer labels.

The PSC filings therefore document the load size, stage, and energization schedule without naming the customer.

The PSC records do not identify OpenAI as the anonymous customer or establish when the 3.2GW load became commercially certain.

Share this article
inXf

Related articles

More
Meta Says Hyperion AI Campus Will Reach 5 GW In Louisiana
Cloud & Data Centers

Meta Says Hyperion AI Campus Will Reach 5 GW In Louisiana

Data Center Knowledge reported that Meta's Hyperion AI campus in Louisiana is being expanded to 5 GW and more than $50 billion of investment, with Entergy filings listing 1,500 MW of new solar and hybrid resources and customer-funded transmission for the expansion.

Spain AI Campus Seeks 300 MW With On-Site Power Plan
Cloud & Data Centers

Spain AI Campus Seeks 300 MW With On-Site Power Plan

Data Center Knowledge reported that EdgeMode, BlackBerry AIF and Mora are seeking regional support for DC MALPICA, a proposed €3 billion ($3.4 billion), 300 MW AI campus whose power model remains partly undisclosed.

Texas Approves $13.8 Billion 765 kV Grid Plan For AI Data Centre Loads
Cloud & Data Centers

Texas Approves $13.8 Billion 765 kV Grid Plan For AI Data Centre Loads

AI data centre customers, final routes or ratepayer cost terms remain outside the public record.

Texas Grid Rules Push AI Data Centres To Pay Interconnection Costs
Cloud & Data Centers

Texas Grid Rules Push AI Data Centres To Pay Interconnection Costs

Texas regulators are moving AI data-centre projects into a stricter grid-planning process that adds financial security, interconnection charges and curtailment disclosure.

PJM Backup-Generator Warnings Test Large-Load Grid Tool
Cloud & Data Centers

PJM Backup-Generator Warnings Test Large-Load Grid Tool

Data Center Knowledge reported that PJM issued emergency backup-generator warnings during a July heat wave but did not dispatch customer-owned generators, leaving total available large-load backup capacity undisclosed.

Finland Data Centre Growth Faces Grid And Heat-Reuse Tests
Cloud & Data Centers

Finland Data Centre Growth Faces Grid And Heat-Reuse Tests

Finland is attracting AI data centre projects because of low-carbon power, cool weather and land, Data Center Knowledge reported, but grid connections, permitting and waste-heat rules now determine how much capacity becomes operational.

Meta Plans $9.17bn Alberta Data Centre With 1GW Power Target
Cloud & Data Centers

Meta Plans $9.17bn Alberta Data Centre With 1GW Power Target

A 1GW Meta data-centre plan in Sturgeon County carries CA$13 billion in expected investment, a Project Greenlight power component and no public first-service or grid-approval timetable.

National Grid Backs Joulent With $1.75 Billion As AI Power Queues Stretch
Cloud & Data Centers

National Grid Backs Joulent With $1.75 Billion As AI Power Queues Stretch

National Grid Ventures plans a $1.75 billion minority investment in Joulent, a power developer built around dedicated generation for AI data centres. The deal supports Project Kilby in Texas, but delivery and interconnection risks remain outside the disclosed timetable.

Keep Reading

More Stories

Latest
G42 Joins Nvidia Secure AI Alliance As Open Models Face Trust TestAIJul 28, 2026G42 Joins Nvidia Secure AI Alliance As Open Models Face Trust TestG42 has joined Nvidia's Open Secure AI Alliance, bringing Abu Dhabi into a group of at least 37 companies backing open AI models for security and sovereign control, The National reported.BitMEX September Shutdown Leaves Users With Force-Close DeadlineFintech & Digital PaymentsJul 28, 2026BitMEX September Shutdown Leaves Users With Force-Close DeadlineBitMEX will shut down in September after 11 years, giving users until Aug. 25 to trade before reduce-only mode and a Sept. 23 force-close deadline, Banking Dive reported.Verizon-Google $1 Billion Fibre Deal Starts 2027 AI Connectivity PushTelco & ConnectivityJul 28, 2026Verizon-Google $1 Billion Fibre Deal Starts 2027 AI Connectivity PushRCR Wireless News reported that Verizon has a $1 billion Google data-centre interconnect deal and expects wider AI-connectivity contracts to begin adding multiple billions of dollars from 2027.Kospi-Nasdaq Correlation Hits 2021 High As AI Memory Trade TightensChips & SemiconductorsJul 28, 2026Kospi-Nasdaq Correlation Hits 2021 High As AI Memory Trade TightensCNBC reported that Rayliant data put the 60-day Kospi-Nasdaq 100 relationship at its highest level since 2021, linking Samsung and SK Hynix more tightly to the U.S. AI hardware trade.Cursor Tests ₹649 India Plan Before SpaceX Deal ClosesAIJul 28, 2026Cursor Tests ₹649 India Plan Before SpaceX Deal ClosesCursor launched a ₹649-a-month India subscription, using local pricing and UPI support to test paid AI coding adoption before its expected SpaceX acquisition closes, TechCrunch reported.Anthropic CEO Separates Open-Weight AI From China RiskCapital & PolicyJul 28, 2026Anthropic CEO Separates Open-Weight AI From China RiskAnthropic CEO Dario Amodei rejected claims that the company wants broad open-weight AI bans, while TechCrunch reported that he still backed chip controls, distillation crackdowns and global safety testing for the most capable models.Anthropic Opus 5 Cuts AI Model Price With Longer-Answer RiskAIJul 28, 2026Anthropic Opus 5 Cuts AI Model Price With Longer-Answer RiskThe Register reported that Anthropic released Opus 5 with token prices below Fable 5, while Artificial Analysis task-cost data and Anthropic guidance leave enterprise buyers with model-choice trade-offs.Nvidia Backstop Talks Add Credit Risk To OpenAI’s 10-Gigawatt Ohio CampusCloud & Data CentersJul 28, 2026Nvidia Backstop Talks Add Credit Risk To OpenAI’s 10-Gigawatt Ohio CampusCNBC confirmed talks over a Nvidia credit backstop of up to $250 billion for OpenAI’s planned 10-gigawatt Ohio AI data centre campus, with lease and construction debt separate from chip purchases.Nebius Sets October 2027 First Phase For 1.2GW Pennsylvania AI CampusCloud & Data CentersJul 28, 2026Nebius Sets October 2027 First Phase For 1.2GW Pennsylvania AI CampusData Center Dynamics identified a 260MW first phase for Nebius’ planned Pennsylvania AI cloud campus, with full buildout at 1.2GW and a dedicated PPL Electric Utilities energy-service agreement.Insilico Phase III Trial Tests AI Drug Discovery TimelinesAIJul 28, 2026Insilico Phase III Trial Tests AI Drug Discovery TimelinesInsilico Medicine has moved Rentosertib into the late-stage clinical record in China, after company disclosures put its fastest AI-supported candidate nomination at nine months.Google Lease Guarantees Put $44bn Behind AI Data CentresCloud & Data CentersJul 28, 2026Google Lease Guarantees Put $44bn Behind AI Data CentresThe Next Web reported that Google has agreed to cover as much as $44bn of data-centre lease payments if tenants default, turning TPU demand from Anthropic and other AI customers into a financing obligation outside owned facilities.Thailand SEC Complaint Sends Bitkub Reporting Case To ProsecutorsFintech & Digital PaymentsJul 28, 2026Thailand SEC Complaint Sends Bitkub Reporting Case To ProsecutorsDecrypt reported that Thailand's SEC filed a criminal complaint against Bitkub and two former directors over allegedly false reports after a 2021 hack, while Bitkub says customer assets were restored.